Megaprojects: Malaysia's Petronas twin towers.
Written in 2015. The following is basically an article written based on several videos I watched regarding the Petronas twin towers. It is presented here for readers to get information on the background of the completion. It is descriptive in nature.
By: Iliyas Ismail
Executive Summary
The
Petronas Twin Towers is located in the heart of Kuala Lumpur, at the designated
Kuala Lumpur City Center (KLCC). In the 1990s, the area was to be developed in
part of Malaysia’s Vision 2020 which would see Malaysia transforming itself
into a developed country by the year 2020. The twin towers would serve as an
important milestone of Malaysia’s modernizing path and it would serve as an
important landmark that would attract the world’s attention.
Construction
took nearly six years, from 1993 to 1997, and was finished before the deadline.
The two towers were given to be handled to two different prime contractors
which were Hazama Corporation for Tower One and Samsung E&C for Tower Two.
These two companies would compete with each other, alongside their team of contractors.
The
project met many setbacks during its constructions and witnessed many delays
along the way. However, the importance of not passing the deadline, due to the
huge cost of the project, required that contractors find a way to always speed
up their process to catch up with their schedule. In the end, the project was a
success.
Introduction
During
the rule of prime minister Mahathir, Malaysia witnessed a fast pace of development in its
vision to becoming a modernized nation. In an effort to make Malaysia stand out and
put it in the world map, Mahathir decided that it would be in the best interest
of the country to build a twin tower skyscraper.
The
goal of the project was to build an eighty-eight storey twin towers, a
mega-project and one that the country has not experienced before. It was not
initially envisioned that it would be the tallest tower in the world at the
time, however, changes in the plans during construction would bring that title
to the towers.
Background
In
further developing the city, the Malaysian government envisioned to build the Kuala
Lumpur City Centre (KLCC) which would be at the heart of the capital city Kuala
Lumpur. The site is the location of a 100- acre colonial era horse race track,
and this would be shifted to the periphery of the city in order to accommodate
the new project. KLCC is to be the main part of the Vision 2020 plan.
The
project planning started in January of 1992, and the design of the towers
architecture was finalized in January 1993. Construction started in April 1993
and was finally finished in October 1996.
The
scale of the project would normally mean that it would be finished in eight
years, however, the Malaysian budget only allows for six years of construction.
This means that workers have to work extra hours to meet the deadline. Any one
day that passes the deadline would cost the builders an additional $700,000.
The
design of the building was tasked to Ceser Pelli of Ceser Pelli and Associates,
for completion. The Prime Minister wanted a building with architecture that
reflects Malaysian culture, a building that would blend with the surroundings.
More specifically, Mahathir wanted a building with an Islamic architecture.
Pelli studied and researched extensively on Islamic architecture and decided to
use the eight-pointed star as the buildings base, a common motive in Islamic
art.
However,
to maximize the floor space area, it was decided arches would be built in
between the eight-pointed star, and thus the building has its design.
In
order to help meet the project deadline, the government decided that contracts
for both the towers would be awarded to two different companies, and they would
be in competition to see who would finish first. This competition is thought to
give more initiatives for the contractors to meet the deadline.
The
first obstacle for the project was the ground conditions. When construction
started, it was discovered that the ground was soft and unstable. Later it was
found out that there was no proper survey carried out on the site before. This would cost the project and additional
thousands of dollars in order to do a survey of the site, before any
construction could begin.
400 exploratory boreholes had to be dug in order to check the soil conditions. The soil was discovered to have an underground cliff. It was later decided that it would be in the best interest of the project, to shift the construction area 60 meters away from the initial site. An interesting initial move indeed.
400 exploratory boreholes had to be dug in order to check the soil conditions. The soil was discovered to have an underground cliff. It was later decided that it would be in the best interest of the project, to shift the construction area 60 meters away from the initial site. An interesting initial move indeed.
When
construction finally started, one of the main challenges faced was the monsoon rain
that regularly falls in a tropical country such as Malaysia. In order to build
a stable and strong building, the team decided to insert 120 meters of steel
columns and solidify them by pumping concrete non-stop for 52 hours. Due to the
heavy rain that consistently fall, a large tent had to be built to cover the
work area from being flooded by water.
The
mega project would consist of participation of companies from many different
countries apart from Malaysia, mainly companies from Japan, South Korea, the
United States, Canada, Singapore and the United Kingdom. Apart from this, there
are foreign workers from across many other countries. There are two consortium
of prime contractors, one for each tower.
Tower
One:
Mayjaus,
a joint venture of:
Hazama
Corporation
MMC Engineering & Construction Co. Ltd.
MMC Engineering & Construction Co. Ltd.
Ho
Hup Construction Sdn. Bhd.
JA Jones Construction Co. Ltd.
Mitsubishi
Corporation
Tower
Two
SKJ,
a joint venture of :
Samsung
Engineering & Construction (Samsung E & C) Co. Ltd.
Dong
Engineering & Construction Co. Ltd.
Syarikat
Jasatera Sdn. Bhd.
Tower
One was headed by the Korean company, Hazama Corp. and was thus known as the
Korean team, while Samsung E&C would lead the team for tower two, the team
known as the Japanese team.
The
bidding process for sub-contractors involved companies having to submit two highly
detailed bid packages. The first was known as the ‘technical proposal’ and the
second is the ‘commercial proposal’. The technical proposal was to determine
the capability of the companies to undertake the project. The technical review
board asked questions such as whether they have the necessary experience, are
they financially stable, whether they have organized with a local partner and
how did this partnering go and so on.
Companies
that satisfy the requirements would go to the second stage of evaluation, which
would be focusing purely on the numbers and calculations. Successful companies
would then be awarded the contracts.
Starting
the project would include the initial plan of developing the idea. The area of
KLCC would have at its center a twin tower skyscraper that would be a source of
tourist attraction. At this stage, all the data for the master plan, including the
project goals, it vision and mission, strategies and risk are formulated and
gathered.
The
second phase is the development phase. Here the tender for the contract is
issued and the planning for the building is sketched out. All the resources
including human, cash and infrastructure are allocated.
The
third phase is when the actual construction begins and is when the peak of the
project is seen, in terms of total effort is exerted. Finally, the project
finishes and a review of the project progress is done.
NTCP
Diamond
Using Shenhar and Dvir's (2007) tool to assess the various aspects of a project, we can further analyze the project, especially with regards to its novelty, technology used, the complexity and also pace of the project.
For
technology wise, as is typical with constructions of many new buildings, there
are very limited numbers of new technologies used. In this case, there wasn’t
any notable new technologies that were mentioned in the literature about the
construction. However, there were several innovative methods of solving
problems this is explained in the coming sections.
For
compelexity, it has a wide dispersed collection of systems, and thus is a very
complex project, involving a consortium of multi-national companies. It also
involves the large scale mobilization of local workers along with foreign
workers on site, with schedules of 24 hours a day.
In
the novelty category, derivative seems to suit the project since there were
many improvements to the existing product, like a new type of concrete were
created, using a mix of concrete with other materials to strengthen it.
However, there were no or very limited new generation of products used or built
throughout the project.
The
pace is time-critical in order not to increase the cost, that were already
anticipated during the project if any problems were to arise.
The
project is categorized as a Project-Based Organization (PBO), with the project
carrying out all business functions usually performed by functional
departments. People would also have to report the project manager instead of a
line manager. For the role of project managers, KLCC Bhd. chose Lehrer
McGovern, a London-based company to assume the role along with them, and Bruce
Schlaitzer was the representative from the latter to hold the role of project
manager.
The
KLCC project was also very adaptive, anticipating problems and having the
expertise to cope with changing or unusual projects.
Hot Spots
During
the project, there were many obstacles that had to be overcome:
1)
The fact that the soil was not suitable for construction. The construction site
had to be moved to another location 60 meters away.
2)
During construction, it was discovered that there was a mistake in the batch of
the mixed concrete materials. This was discovered after one of the batches
failed a routine testing of materials.
The
concrete had to be of a certain strength to withstand from collapsing.
Construction immediately grinded to a halt and the worry was how much of the
concrete mix had already been used in constructing the towers. This triggered
many debates on how to proceed and became a big issue, since tearing down the
building would be costing the project very high. After careful checking and
testing however, it was found that only one floor prior, was built using the
flawed concrete mix, and thus the entire floor was demolished.
3)
Floor-laying of the building was the most time consuming of the entire process.
The planned scheduling for one floor to be completed was 10 days, however due
to the halt in problem number two, precious time was wasted and the time for
this process had to be shortened.
When
laying the floor of a building, the next floor clearly cannot be completed
until the one below it is done. This resulted in a bottleneck. A revised method
of the floor laying process managed to cut down the time to complete from 10
days to only 4 days. However, this increased the workload and workers
effectively had to work for seven days a week, and the process was 24 hours
non-stop.
4)
When construction reached to the 72nd floor, a new report unveiled
another major problem. Human errors had resulted in tower one being slightly
off tangent by 25mm. Although a small deviant, if they were to continue
unabated, the problem would only worsen and the tower would lose its straight
structure.
After
careful deliberations, the solution was for the construction to continue 2mm at
the opposite direction, for the rest of the 16 remaining floors. This caused a
setback for the contractors and delayed the project while they had to make
calculations and change their plans.
Innovative methods
1)
The pouring of concrete for 52 hours without break, one truckload on an average
of one for every minute. 13, 000 cubic meters of concrete was pumped after the
steel laid in bored holes, and it was the biggest concrete slab in the
country’s history.
The
logistics system used to ensure that truck-loads of concrete mix would arrive
without break was complex and innovative.
2)
The building would have the world’s deepest foundation at the time, with 120
meters of steel being planted in the ground to gain maximum stability.
3)
The usage of strong concrete is unique in this project. The towers would be
built using 16 concrete pillars, linked by beams to support a weight of 270,000
tones. No building of such scale was
constructed using concrete pillars before, usually its other materials like
steel, as concrete would collapse under such weight. However, concrete is in
abundance in Malaysia and steel would cost the project too high.
In
order to obtain this, testing was done in Chicago to come up with a strong
combination of raw materials to create the suitable concrete mix that could
withstand pressure. The condition was that the raw materials used are only
those that could be found in Malaysia, so that none would have to be imported.
4)
In delivering the concrete up the building, they used powerful pumps delivered
from Germany, and broke the record for the highest continuous pump.
5)
The building of the sky bridge was an engineering challenge. In order to
prevent it from collapsing by movements of the towers due to wind, an
innovative solution was designed which was to use spherical bearings. These would
allow the bridge to move along with the building.
Appropriate and
inappropriate approaches
Overall
the project was a major success, as it met the original deadline which would
have otherwise cost thousands of dollars in losses for every day passed. There
were some areas of improvements, such as the need to ensure that a proper
survey of the land area chosen has already been done before actual construction
begins. The survey done on the area was not very comprehensive, and it was
thought that the area would be suitable especially because it was the site of a
building housing the Selangor Turf Club before.
All
the materials that are to be transported to the construction should and must be
tested before being used. The mistake of a party mixing the materials should be
avoided in the first place by conducting proper monitoring. A mistake of using
the wrong materials would be very costly to any given project in correcting
that mistake, especially if it involves tearing down part of a finished
building.
Managing
a low technology project without incurring too much cost in using an approach
of a high-technology cost is noted to be important to not increase anymore
cost. Any measures possible, should be taken to try to reduce the amount of
hours of completion for any work package, and the ability to reduce the amount
of days to complete the floor layering process is to be commended as an
excellent move.
Conclusions
Presently,
the Petronas Twin Towers has served its purpose well without any problems in
its design or structure. The proper bidding process and the awarding of
contracts to companies that were really able to undertake the project proves to
be an important factor to the success. There was no major setbacks that could
not be solved, although what needed to be done was to increase the workload for
workers, which resulted in mistakes occurring.
However,
the successful construction at the end meant that the teams were competent
enough to overcome these errors and deliver the project successfully.
Comments
Post a Comment